|
McCool
and Associates, P.C.
A R C H I T E C T U R E A
N D P L A N N I N G , A P R O F
E S S I O N A L C O R P O R A T I O N
Value Engineering Study - New
East Side Fire Station
Tulsa Fire Department
- Three Station Building Program
"I particularly want to commend you
for the way your Value Engineering team was able to fit in with the design team.
Because of the very nature of a VE study, there is a good chance that an
adversarial relationship will develop between the VE team and the Design
Team. You were able to avoid that pitfall and come across in a positive
way. This positive relationship had a major impact on how much of the
proposed costs reductions were adopted."
J. D. Turner, P.E.f Tulsa Public Works Department, Engineering
Services
MAPC assembled a multi-disciplined team to
conduct the Value Engineering Study of the 75 % construction documents for the
new Eastside Fire Station in Tulsa, Oklahoma, as requested by the City of Tulsa
and the Tulsa Fire Department. It was the team’s objective to analyze the
project, find high cost areas, and identify alter natives for reduced cost or
improved functional use of the facility or functional improvements in the plan.
The design architects estimated costs of the station was $2.2 million at the
beginning of the study.
The study was a 2 ˝ day workshop with a Certified Value Specialist, an architect,
structural engineer, mechanical engineer, and electrical engineer as team
members. The recommendations prepared during the study were included in the
final report.
The VE job plan included the following phases::
Informative Phase –review construction documents in terms of function and associated costs – breakdown
construction costs into system groups for comparative analysis.
Speculative Phase – develop ideas and ways to provide
necessary functions at a lower initial cost.
Analytical Phase – evaluation of ideas in terms of cost and
probability of implementation, magnitude of possible savings, and state of the
art technology.
Development Phase – selected ideas are expanded into workable
solutions – develop description of advantages and disadvantages of
recommended designs.
Presentation Phase – presentation of findings to client.
Report Phase – issue report for client’s use.
From a total of 71 ideas listed during the speculative phase of the
VE job plan, the value engineering team developed fifty proposals for a
substantial cost savings as illustrated below:
Discipline
Recommendations
Est. Cost Savings
(G)
General
3 $
227,757.00
(C)
Civil
5 $
24,925.00
(S)
Structural
12 $
129,905.00
(A)
Architectural
15 $
210,036.00
(M)
Mechanical
4 $
19,325.00
(P)
Plumbing
5 $
5,900.00
(E)
Electrical
6 $
19,431.00
$ 637,279.00
The estimated savings were generated from unit costs provided by the design
architects, Fritz Baily, Inc.. The costs savings implemented
on all three new stations totaled nearly 30 times the
costs of the study and will be used as a benchmark for future station planning.
|